2020年軟考高級信息系統(tǒng)項目管理師考試英語練習題十六
1.Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with,project stakeholders. The ( ) is useful responsible for stakeholder management.
A. PMO B. CIO C. CCB D. PM
【答案】D
【解析】
項目干系人管理是指為滿足干系人的需要而與之溝通,并解決所發(fā)生的問題,通常,項目經(jīng)理(PM)負責項目干系人管理。
A.項目管理辦公室
B.首席信息官
C.變更控制委員會。
D.項目經(jīng)理
2.The most crucial time for project risk assessment is ( ).
A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published
【答案】B
【解析】
進行項目風險評估最關鍵的時候是.規(guī)劃階段
A.問題出現(xiàn)時
B.規(guī)劃階段
C.結(jié)束階段
D.項目進度公布后
3.A data warehouse is a subject-oriented data set used for reporting and analusis. Data warehouses can be subdivided into ( ). Which store subsets of data from a warehouse.
A . OLTPs B. transactions C. data sarts D. OLAPs
【答案】C
【解析】
數(shù)據(jù)倉庫是一個面向主題的用于報告和分析的數(shù)據(jù)集。數(shù)據(jù)倉庫可以細分為數(shù)據(jù)集市,即從一個倉庫中存儲數(shù)據(jù)的子集。
A.聯(lián)機事務處理
B.交易
C.數(shù)據(jù)集市
D.聯(lián)機分析處理
距離2020年軟考高級職稱準考證打印還有一段時間,考生可提前 免費預約短信提醒服務,屆時會提示您2020年軟考高級職稱準考證打印時間.考試時間,讓您安心備考。
以上內(nèi)容為2020年軟考高級信息系統(tǒng)項目管理師考試英語練習題十六,小編為廣大考生上傳更多2020年軟考高級職稱考試歷年真題、模擬試題等供大家學習,如有需要請點擊文章下方“免費下載”獲取相關內(nèi)容。
最新資訊
- 軟考高級題庫「信息系統(tǒng)項目管理師」每日5題(12月20日)2024-12-20
- 軟考高級題庫「信息系統(tǒng)項目管理師」每日5題(12月19日)2024-12-19
- 備考干貨:軟考高項經(jīng)典計算題跟練(5)2024-12-17
- 備考干貨:軟考高項經(jīng)典計算題跟練(4)2024-12-16
- 備考干貨:軟考高項經(jīng)典計算題跟練(3)2024-12-13
- 備考干貨:軟考高項經(jīng)典計算題跟練(2)2024-12-12
- 軟考高級題庫「信息系統(tǒng)項目管理師」每日5題(12月11日)2024-12-11
- 軟考高級題庫「信息系統(tǒng)項目管理師」每日5題(12月10日)2024-12-10
- 軟考高級題庫「信息系統(tǒng)項目管理師」每日5題(12月9日)2024-12-09
- 軟考高級題庫「信息系統(tǒng)項目管理師」每日5題(12月6日)2024-12-06